By Shlok Gandhi
Imagine a contractor working on a home renovation when the homeowner requests a few additions. After a quick discussion, the homeowner says, "Looks good. Go ahead." The contractor completes the additional work, but when the final invoice arrives with an extra $2,500, the homeowner disputes the charge. They understood the work was included in the original price, while the contractor understood it was an approved extra.
This is how a seemingly simple change to a construction project can turn into a costly dispute. The question is no longer whether the work was completed, but what was actually agreed to and whether that agreement can be proven. So, are verbal approvals and text messages enough to create a binding change order in Ontario? The short answer is that they can be. However, whether they establish an enforceable agreement depends on the contract, the circumstances, and the evidence available.
When Does a Change Order Become Binding?
Construction projects rarely unfold exactly as planned. Homeowners request upgrades, contractors encounter unexpected conditions, and changes to the original scope of work become necessary. A change order documents these adjustments, including any changes to the work, price, or schedule. Most construction contracts outline how changes must be approved, often requiring written authorization before additional work begins. In practice, however, decisions are frequently made through phone calls, text messages, or conversations on-site.
The problem is that agreeing to additional work is not necessarily the same as agreeing to an additional price. For example, a homeowner might approve the installation of extra pot lights without discussing the cost. When the contractor later charges $2,500, the homeowner may dispute the amount, even though they requested the work. The contractor may have proof that the work was authorized, but establishing that the homeowner agreed to the price is another matter. That distinction is often where disputes begin.
What Does Ontario Law Say?
Under Ontario contract law, verbal agreements can be enforceable. However, where an existing construction contract requires written change orders, that requirement becomes particularly important. Courts may consider not only the written contract but also how the parties behaved throughout the project. For instance, if an owner routinely approves extra work by text message and pays the resulting invoices without objection, that history may become relevant when a later change is disputed.
In Reid v. Xiao, 2021 ONSC 7468, the court considered a dispute involving additional construction work and the parties' approach to the contractual change-order requirements. The decision illustrates that the parties' conduct may affect how those requirements are applied. However, even where formal approval procedures have not been followed, a contractor must still establish entitlement to the payment claimed. In other words, proving that extra work was performed is not necessarily enough to prove that the full amount charged is owed.
When assessing such disputes, courts may examine the communications between the parties, whether pricing was discussed, who authorized the changes, and how previous extras were handled. The absence of a signed change order does not automatically settle the dispute in either party's favour.
Can a Text Message Count as Approval?
Text messages can be valuable evidence in construction disputes, but their wording matters. Consider the difference between a homeowner responding, "Yes, go ahead," and stating, "I approve the installation of six additional pot lights for $2,500 plus HST, as discussed." Both suggest approval, but the second provides a much clearer record of what was agreed to.
A simple written confirmation identifying the additional work, its cost, and any changes to the schedule can help prevent disagreements later. However, if the construction contract specifically requires a formal signed change order, a text message should not automatically be treated as a substitute. Following the approval process outlined in the contract remains the safer approach for both parties.
What Happens When Payment Is Disputed?
When a contractor and homeowner disagree over extra charges, the dispute often comes down to the available evidence. For a contractor, this might include messages authorizing the work, estimates, invoices, labour records, and material costs. For a homeowner, the original contract, agreed scope of work, previous invoices, and communications may help establish whether the extras were authorized or already included in the original price.
The important question is not simply whether additional work was completed, but whether the parties can establish what was approved, by whom, and on what terms. Where those details remain unclear, even a relatively small invoice can lead to an expensive disagreement.
Final Thoughts
Construction projects often become less formal as they progress. Once trust develops, quick conversations and text messages can replace the paperwork originally contemplated by the contract. While this may seem convenient at the time, it can create problems when the parties later disagree about what was promised.
Verbal approvals and text messages can carry legal significance in Ontario, but their enforceability depends on the contract and the circumstances. For both contractors and homeowners, taking a few minutes to confirm the scope, price, and authorization of additional work can prevent much bigger problems down the road.
Case Reference: Reid v. Xiao, 2021 ONSC 7468.
